Nov 13, 2026, 3:20 PM ET JPMorgan lowers Lithium Americas price target to $5 from $6, maintains Overweight AI-generated summary · Source: press report
NYSE / TSX: $LACThacker Pass · constructionDOE and GM funding structurePhase 1 capex now $3.83B

LAC Stock Hub: Lithium Americas News, Thacker Pass and Funding

Lithium Americas is building Thacker Pass through a joint venture owned 62% by LAC and 38% by GM. At September 30, 2026 cash and restricted cash totaled $1.2587 billion – $961.604 million of cash and $297.068 million of restricted cash – including $359.5 million at the joint venture, and are not a single unrestricted corporate wallet. Nine-month operating and investing cash use reached $1.0602 billion, funded by DOE loan advances, the Yorkville debentures and public offerings. The third quarter, reported on November 12, showed net income of $90.1 million driven by $92.9 million of fair-value gains on the JV warrant and the convertible debt rather than by operations, and a diluted net loss per share of $0.05; the November 11 capital cost estimate for Phase 1 remains $3.83 billion, with mechanical completion targeted for late 2027.

Last updated: November 12, 2026Financial period: September 30, 2026Currency: USD
Research Library
Lithium Americas ($LAC), research updated November 12, 2026
20 pages covering the third-quarter 2026 results reported on November 12, $1,258.7 million of cash and restricted cash at September 30, the $3.83 billion Phase 1 budget and its funding plan, the grid-connection target, DOE loan conditions, Yorkville conversion and dilution, sources and FAQ. This is dated research; the hub follows later developments. For personal use only: redistribution prohibited.
Get the report (PDF)
Next dated milestone · construction target
By year-end 2026 · grid connection and energization

The third quarter was reported on November 12: net income of $90.1 million, mostly fair-value gains on the JV warrant and the convertible debt, cash and restricted cash of $1.2587 billion at September 30 and 377,334,749 shares outstanding at November 11. The company targets connecting the electrical utility grid to the site substation and energizing certain key process-plant components by the end of 2026; mechanical completion remains targeted for late 2027, with ramp-up through 2028. A target is not confirmation of completion. November 11 project update →

Updated budget: the definitive Phase 1 capital cost estimate is $3.83 billion including contingency, up from $2.93 billion, and 2026 capex guidance rises to $1.7–2.0 billion from $1.3–1.6 billion. The company attributes the increase mainly to labor install rates (about $245 million), craft wages, EPCM and contractor wages (about $150 million each), EPCM staffing and tariffs and logistics (about $100 million each) and an additional 10% contingency (about $150 million). Company release.
LAC daily stock chart from Finviz
Daily chart $LAC. Source: Finviz, for information only. Chart link is an affiliate link. Interactive chart with bull and bear scenarios on JC Just Charts →

LAC stock: dated key data

Stock price · live
Real-time price, volume and moving averages for $LAC on JC Just Charts.
Cash and restricted cash
$1,258.7M
September 30, 2026: $961.604M of cash and $297.068M of restricted cash, including $359.5M at the joint venture.
Restricted cash
$297.068M
September 30, 2026; DOE advances are held in restricted accounts.
Nine-month operating + investing use
$1,060.2M
From the Form 10-Q: $21.129M operating plus $1,039.068M investing; financing excluded.
Reported common shares
377.335M
377,334,749 at November 11, 2026 (company release); 377,335 thousand on the September 30 balance sheet.
DOE loan carrying value
$1,196.3M
September 30, 2026, net of deferred financing costs; $1.448B of advances drawn was reported in the November 11 update.
Yorkville initial closing
$150M
Debentures issued August 13, 2026; subsequent to June cash.
LAC project interest
62%
Thacker Pass JV at September 30, 2026; GM holds 38%, before effects of separate project warrants.

Financial and ownership data: September 30 Form 10-Q and results release (Form 8-K exhibit 99.1); Yorkville closing and conversion: Closing filing and Resale registration; market reference: closing price of the regular session. DOE advances and the capex estimate: November 11 project update. Joint-venture balances are already included in the consolidated figures, not additional funds.

LAC today: construction progress and the funding bridge

Third quarter of 2026, reported November 12. The Form 10-Q for the period ended September 30, 2026 reports a net income of $90.1 million against a net loss of $199.2 million a year earlier, of which $74.7 million is attributable to LAC stockholders, and a diluted net loss per share of $0.05. The result comes from $53.6 million of fair-value gains on the JV warrant, $39.3 million on the convertible debt and its conversion feature and $5.2 million on the convertible debt measured at fair value, not from operating revenue, which is nil while Thacker Pass is under construction. Cash and restricted cash were $1,258.7 million at September 30, and 377,334,749 shares were outstanding at November 11. Form 8-K · Form 10-Q.

November 11 project update. Lithium Americas completed a definitive capital cost estimate for Thacker Pass Phase 1 of $3.83 billion including contingency, up from $2.93 billion, and kept mechanical completion targeted for late 2027 with ramp-up through 2028. It estimates the resulting incremental funding requirement at about $995 million ($895 million of extra capex, $58 million of higher Sustaining Capex Reserve Account requirements and a net $42 million of other items) and expects to meet it through $650 million of company contributions at the joint-venture level and, as and when required, $315 million currently credited to DOE loan reserve accounts, plus a reduction of about $30 million in the Sustaining Capex Reserve Account requirement, under a loan amendment (OWCA 3) signed November 10 and agreements with the DOE and GM; the contributions will increase the company’s ownership percentage in the joint venture. The September 30 balance sheet confirms about $1.2587 billion of total cash and restricted cash, including $359.5 million at the joint venture. CEO Jonathan Evans said the anticipated capital cost is expected to remain funded. Company release.

Phase 1 is designed for nominal annual capacity of 40,000 tonnes of battery-quality lithium carbonate. It is a construction-stage project with no reported operating revenue, not an operating mine delivering that output. Mechanical completion and the planned 2028 ramp-up remain distinct from commercial production and cash generation. Project update · Annual development schedule.

Construction spending dominates the cash picture. The calculated $109.231M monthly first-half operating-plus-investing average is historical, not a cash-exhaustion forecast. DOE conditions, reserve funding, the revised cost estimate and actual equity issuance must be reconciled with work completed. June accounts and loan conditions.

Main risk: Cost inflation, delayed commissioning or restricted funding access may extend spending before production. Project partners, debt, royalties, warrants and new common shares can reduce the economics available to an existing shareholder even as construction advances.

Constructive case

If the November 11 plan covers the higher $3.83B budget through company contributions and existing DOE reserve accounts, energization and installation on schedule could reduce execution uncertainty. Accessible project draws, contained costs and eventual saleable output would strengthen the operating case.

Cautious case

The budget has already risen by $900M to $3.83B, and $650M of the new requirement must come from the company itself; further cost growth or delay could stretch the funding bridge. Lower applicable Yorkville conversion prices can increase share issuance, while project claims and commodity-price risk persist before cash generation.

LAC stock news: six selected updates

Nov 13, 2026

JPMorgan lowers Lithium Americas price target to $5 from $6, maintains Overweight

JPMorgan cut its price target on Lithium Americas to $5 from $6. The bank kept its Overweight rating on the stock. Analyst action reported by the press; it is the bank's view, not Merlintrader's.

Nov 12, 2026

Lithium Americas reports third-quarter results with $74.7 million in earnings

Lithium Americas reported earnings of $74.7 million for its third quarter. The Vancouver-based company posted a net loss of 5 cents per share. Earnings adjusted for one-time items were 12 cents per share. Reported by the press from an official company announcement; the primary document was not yet available in our sources at the time of writing.

Nov 11, 2026

Lithium Americas Provides Thacker Pass Project Update

Mechanical completion of Thacker Pass Phase 1 is targeted for late 2027, with ramp-up through 2028 and nominal production of 40,000 tonnes per year of battery-quality lithium carbonate at full capacity. The updated definitive Capex Estimate for Phase 1 is $3.83 billion including contingency, up from $2.93 billion. As of September 30, 2026, approximately 1,900 personnel were on site and procurement was over 90% completed.

Sep 11, 2026

Corporate-development executive retirement disclosed

The vice president retired following September 8 notice. The company said the departure did not result from disagreement over operations, policies or practices. It is an executive change, not a financing closing or evidence of an insider share sale.

Aug 17, 2026

Yorkville elects an initial debt conversion

The resale prospectus disclosed an August 13 election to convert $15M principal into 5,232,679 common shares. Conversion changes the debt and share denominator; it is not a second $15M cash receipt.

LAC stock catalysts: dated milestones

  • November 11, 2026 · Project updateCompleted · company release

    Phase 1 capex estimate raised to $3.83B from $2.93B; about $995M of incremental funding expected from $650M of company contributions and $315M of DOE reserve-account funds; DOE loan amendment (OWCA 3) signed November 10; late-2027 mechanical completion maintained. Company release.

  • November 12, 2026 · Q3 resultsReported · company release and Form 10-Q

    Net income of $90.1 million, including $53.6 million of JV warrant and $39.3 million of convertible-debt fair-value gains; diluted net loss per share $(0.05); cash and restricted cash $1,258.7 million at September 30; 377,334,749 shares outstanding at November 11; 1.1 million shares sold through the ATM in the quarter for $4.1 million of net proceeds. Results release · Form 10-Q.

  • By year-end 2026 · Grid connection and energizationCompany target restated November 11 · not confirmed completion

    Connecting the electrical utility grid to the site substation and energizing certain key process-plant components, alongside the final equipment deliveries, structural concrete foundations and early utility commissioning. Upcoming construction milestones.

  • Late 2027 · Phase 1 mechanical completionCompany target · not commercial output

    Completion of construction precedes the production ramp and depends on cost, schedule, commissioning and funding.

  • 2028 · Production ramp-upCompany development schedule · execution dependent

    The annual schedule anticipates ramp-up after mechanical completion. Nominal capacity is not a guarantee of saleable output or profit.

Thacker Pass: remaining cost, commissioning and partner economics

Build

Progress must retire work

Engineering and procurement need to become installed, commissioned equipment. Spending can rise during peak construction without itself proving a delay or success.

Ownership

Consolidation is not 100% economics

The 62%/38% JV split matters for eventual distributions. Consolidated accounts include JV balances but do not assign all future project cash to LAC common holders.

Resource

Production remains ahead

A large resource and strategic offtake support the rationale, while recovery, throughput, operating costs and lithium prices determine realized economics.

As of September 30, 2026 the company reports detailed engineering completed, procurement over 90% complete, over 80% of third-party contract value committed and over 50% incurred, and about 1,900 personnel on site, rising to about 2,200 by year-end 2026; it names attraction and retention of craft labor and planned installation rates as the primary remaining cost risks. November 11 update. Construction-cost updates and the remaining budget should be tested against the funding actually accessible at the required time. June disclosure · August operating update.

LAC DOE conditions, Yorkville conversion and dilution

The approximately $2.23B DOE facility includes capitalized interest and funds eligible project costs. The $1.209B advanced by June is different from the $988.018M accounting carrying value. Future advances and reserves remain subject to loan terms; the amendment required an additional $120M of reserve funding within twelve months of October 7, 2025. On November 11 the company said it contributed that $120M on October 7, 2026 and that cumulative DOE advances reached $1.448B after a fourth advance of $239.0M on August 21, 2026. Under a third omnibus waiver, consent and amendment (OWCA 3) signed November 10, 2026 and agreements with the DOE and GM, $315M currently credited to DOE loan reserve accounts can be used as and when required for the higher budget, and the Sustaining Capex Reserve Account requirement decreases by about $30M during and after ramp-up. The company is working with the DOE and GM to finalize the implications for joint-venture interests. Under the March 2026 ATM program it has sold 14.2 million shares at an average $5.25 for $72.6M net to date (1.1 million in Q3 at an average $3.87), leaving $175.7M of capacity. November 11 update.

The Yorkville mechanism provides financing alongside variable conversion exposure. Actual conversion prices, shares issued and any later draw determine the result. The structure also includes separate corporate and JV warrants associated with DOE and other partner or royalty claims. A project financing headline is not an equivalent amount of freely distributable corporate cash. Loan and capital notes · Yorkville closing · Conversion and resale terms.

Merlintrader Health Score · LAC

2.65out of 5
Balance sheet and cash · 30%3 / 5

Cash and restricted cash of $1,258.7M at September 30, 2026 support construction, but the November 11 budget increase to $3.83B requires about $995M more, $650M of it from company contributions; restricted JV funds and spending constrain flexibility.

Catalysts · 30%3 / 5

The revised budget, the funding plan and the third-quarter results are now disclosed; grid connection and energization by year-end 2026 are testable, while completion and ramp-up remain targets.

Dilution · 20%1.5 / 5

Variable Yorkville conversion, ATM issuance, warrants and compensation can expand the denominator.

Liquidity · 10%3 / 5

Executed DOE advances are concrete, while further draws and uses remain conditional.

Execution · 10%2.5 / 5

Construction has advanced, while installed systems, commissioning and remaining cost are decisive.

Editorial assessment dated November 12, 2026, after the third-quarter results (previous score 2.65, November 11, 2026; scores unchanged): 3×30% + 3×30% + 1.5×20% + 3×10% + 2.5×10% = 2.65/5. This describes robustness, not value, a commodity-price forecast, a target price or an investment recommendation.

LAC red flags

  • Consolidated and JV cash must not be double-counted or treated as one unrestricted pool.
  • Remaining DOE commitment is conditional funding, not immediately available cash.
  • The Phase 1 capex estimate rose to $3.83B from $2.93B on November 11; further cost inflation or commissioning delays can extend the funding bridge.
  • Yorkville conversion prices and other issuance affect the actual share denominator.
  • Mechanical completion, ramp-up and profitable production are different milestones.
  • Partner interests, debt, royalties and warrants affect common-share economics.
  • Lithium prices, permitting and environmental obligations remain relevant.

LAC Stock FAQ: Lithium Americas Questions Answered

When is the next Lithium Americas Thacker Pass catalyst?

The next dated milestone is the company’s target of connecting the electrical utility grid and energizing key process-plant components by year-end 2026, after the third-quarter results reported on November 12, 2026. The November 11 project update targets grid connection to the site substation and energization of certain key process-plant components by the end of 2026, with Phase 1 mechanical completion in late 2027 and ramp-up through 2028. November 11 project update. Construction milestones. Development schedule.

Does Lithium Americas generate revenue?

Lithium Americas had no operating revenue in the six months ended June 30, 2026 while Thacker Pass remained under construction. Phase 1 is designed for nominal annual capacity of 40,000 tonnes of battery-quality lithium carbonate; revenue depends on completing, commissioning and ramping the project. Financial statements. Project design and construction.

How much cash does Lithium Americas have, and how long will it last?

Lithium Americas reported $961.604 million of cash and $297.068 million of restricted cash at September 30, 2026, $1,258.7 million in total and including $359.5 million at the joint venture. Nine-month operating and investing cash use was $1,060.2 million, and the November 11 capital cost estimate for Phase 1 is $3.83 billion, with about $995 million of additional funding to be met through $650 million of company contributions and $315 million credited to DOE reserve accounts. Project restrictions, future eligible loan draws and remaining construction costs determine funding coverage. Form 10-Q · November 11 project update.

Is LAC stock at risk of dilution?

Yes: Lithium Americas issued $150 million of Yorkville convertible debentures on August 13, 2026, creating potential common-share issuance under variable conversion terms. A later debt-to-share conversion reduces debt rather than bringing in fresh cash. Corporate and project warrants add other potential ownership dilution. Initial debenture closing. Conversion and resale terms. Capital structure.

When does Lithium Americas report earnings?

Lithium Americas reported its third-quarter 2026 results on November 12, 2026, with the Form 10-Q for the period ended September 30, 2026; the company has not announced a date for its full-year 2026 results. Results release · Company financial calendar.

What does Lithium Americas do?

Lithium Americas develops the Thacker Pass lithium project in Nevada through a joint venture owned 62% by the company and 38% by General Motors. It is building Phase 1 to produce battery-quality lithium carbonate; the project remains in construction ahead of commissioning and production ramp-up. Business and joint venture. Project development.

How much DOE funding is available to Lithium Americas?

The approximately $2.23 billion DOE facility includes capitalized interest; cumulative cash advances reached $1.448 billion after a fourth advance of $239.0 million on August 21, 2026. Under the loan amendment signed November 10, 2026, $315 million currently credited to DOE loan reserve accounts can be used as and when required toward the higher Phase 1 budget. Further advances depend on eligible costs, reserves and loan conditions. The undrawn headline amount therefore cannot be counted as unrestricted cash already available to Lithium Americas. DOE loan and funding conditions. November 11 project update.

Primary sources

Lithium development projects face construction delays, cost overruns, permitting and environmental risks, commodity-price volatility, financing constraints and dilution. Commercial production and cash generation are not guaranteed, and investors may lose some or all of their capital.

Disclaimer. Editorial content for education and information. This is not financial advice, an investment recommendation under CONSOB or applicable European rules, or an offer or solicitation to buy or sell securities. Forecasts and scenarios are uncertain; figures retain their stated dates. Merlintrader may hold positions in securities discussed. Affiliate links, including Finviz, may generate commissions without additional cost to the reader.